Borrowdale Office Park
PROJECT 014 · HANDED OVER 2025

BORROWDALEOFFICE PARK

Four-storey steel-framed offices, fabricated in Msasa and erected in 11 months — zero lost-time incidents.

BORROWDALE, HARARECOMMERCIALSTEEL FRAME4 200 M²
CONSTRUCTION PROGRESS
100%
THE PROJECT

STEEL UP IN ELEVEN
MONTHS. FLAT.

01THE BRIEF

4 200 m² of grade-A offices on a tight Borrowdale plot, with a fixed handover date for a signed anchor tenant.

02OUR APPROACH

A bolted steel portal frame fabricated in Msasa while foundations cured; bays lifted at night to keep the road open.

03THE RESULT

Handed over two weeks early, zero lost-time incidents and 18% less steel than the concrete-equivalent design.

11MOProgramme
380TSteel
0LTIIncidents
ON SITE · 42 PHOTOS

FROM SLAB
TO SKYLINE.

steel erection · level 03
01STEEL ERECTION · L03
night lift · bay 4
02NIGHT LIFT
composite deck pour
03DECK POUR
façade fins going up
04FAÇADE FINS
BUILD SEQUENCE

FROM GROUND
TO HANDOVER.

01foundations stage
APR – JUN 2024
FOUNDATIONS

Pad footings and a 1 100 m³ raft, poured in eight sequences.

02steel stage
JUL – OCT 2024
STEEL

380 t bolted portal frame, lifted bay by bay at night.

03roofing stage
NOV – DEC 2024
ROOFING

Standing-seam roof and plant deck, sealed before the storms.

04finishing stage
JAN – MAR 2025
FINISHING

Fin façade, MEP fit-out — handed over 14 days early.

“Massive gave us a fixed date and then beat it. The steel went up at night while Borrowdale Road stayed open, and our anchor tenant moved in on day one.”
TENDAI MOYODevelopment Director · Zambezi Property Fund
MORE FROM THE SITE PLAN

RELATED PROJECTS

Start Your Project

GOT A SITE LIKE THIS ONE? LET'S TALK.

Free site visit and fixed quote within 48 hours, anywhere in Zimbabwe.

+263 77 412 8860
Call Now WhatsApp